Justia Massachusetts Supreme Court Opinion Summaries

Articles Posted in Construction Law
by
The Supreme Judicial Court held that the housing appeals committee had jurisdiction over the projects at issue in this case and the power to remove or modify conditions that made such projects significantly more uneconomic.Under the Massachusetts Comprehensive Permit Act, Mass. Gen. Laws ch. 40B, 20-23, qualifying developers of low or moderate income housing have access to a comprehensive streamline permitting process and expedited appeal before HAC. The Act further authorizes HAC to strike or modify any conditions on a comprehensive permit application that would make it "uneconomic" to proceed with a project. At issue was whether the HAC has the power to reject conditions where a project has received a funding commitment from a public subsidizing agency and the developer receives a comprehensive permit subject to conditions but the rate of return for the original proposal is found to be uneconomic and HAC determines that the imposed conditions make the project "significantly more uneconomic" and therefore rejects them. The Supreme Judicial Court answered the question in the affirmative, holding that HAC is authorized to eliminate conditions that effectively prevent such projects by rendering them significantly more uneconomic. View "Zoning Board of Appeals of Milton v. HD/MW Randolph Avenue, LLC" on Justia Law

by
In this case, the Supreme Judicial Court responded to a certified question posed by a judge in a federal district court concerning the application of the six-year statute of repose in Mass. Gen. Laws ch. 260, 2B to claims regarding alleged defects in the design and construction of the common areas of a multi-building, multi-phase condominium.The Supreme Judicial Court answered (1) regardless of how many phases of the development there may be or how many buildings are within each phase, where a condominium development is comprised of multiple buildings each building constitutes a discrete improvement for purposes of Mass. Gen. Laws ch. 260, 2B such that the opening of each individual building to its intended use or the substantial completion of the individual building and the taking of possession for occupancy by the owner triggers the statute of repose under section 2B with respect to the common areas and limited common areas of that building; and (2) where a particular improvement is integral to, and intended to serve, multiple buildings the statute of repose begins to run when that discrete improvement is substantially complete and open to its intended use. View "D'Allessandro v. Lennar Hingham Holdings, LLC" on Justia Law

by
In this case involving procedures and remedies for impermissible peremptory challenges the Supreme Judicial Court adopted the language of the Federal standard for the first step of a challenge pursuant to Batson v. Kentucky, 476 U.S. 79 (1986), and retired the language of "pattern" and "likelihood" governing the first-step inquiry under Commonwealth v. Soares, 444 U.S. 881 (1979).While incarcerated, Defendant argued on appeal and in pursuing postconviction relief that the trial judge did not appropriately inquire as to whether the prosecutor unconstitutionally struck African-American men from the jury. The Appeals Court determined that the trial judge did not err in deciding not to continue past the first step of the Batson-Soares inquiry. In granting Defendant's petition for writ of habeas corpus, the First Circuit concluded that the trial judge unreasonably applied Federal law. Defendant then filed a motion for a new trial or, in the alternative, for a reduced sentence. The motion judge reduced the verdict under Mass. R. Crim. P. 25(b)(2) and resentenced Defendant. The Supreme Judicial Court vacated the order and remanded for retrial, holding (1) the judge improperly reduced the verdict, and the principles of double jeopardy did not preclude retrying Defendant; and (2) adopting the Federal formulation of the Batson-Soares test will better identify improper peremptory challenges. View "Commonwealth v. Sanchez" on Justia Law

by
In this case involving a claimant seeking to enforce a target lien bond by commencing a civil action pursuant to the mechanic's lien statute, Mass. Gen. Laws ch. 254, 14, the Supreme Judicial Court vacated the superior court's order allowing Defendant Arch Insurance Company's (Arch) summary judgment, holding that the lien statute contains no requirement that the claimant record an attested copy of the complaint in the registry of deeds.City Electric Supply Company (CES) supplied electrical materials for a construction project in Brookline and perfected a mechanic's lien on the Brookline property. Later, general contractor Tocci Building Corporation issued and recorded a target lien bond in the amount of the mechanic's lien CES had created. The target lien bond listed Arch as surety. CES then filed an action against Arch seeking to enforce the target lien bond. A superior court judge granted summary judgment for Arch, concluding that suit on a lien bond requires an attested copy of the complaint to be recorded. The Supreme Judicial Court reversed and remanded the case, holding that a party seeking to enforce a target lien bond need not record a copy of a complaint in the registry of deeds as a condition precedent to enforcing the bond. View "City Electric Supply Co. v. Arch Insurance Co." on Justia Law

Posted in: Construction Law
by
The Supreme Judicial Court affirmed the superior court’s dismissal of this complaint under the statute of repose, holding that a claim alleging that a building contractor committed an unfair or deceptive act under Mass. Gen. Laws ch. 93A, 2 and 9 by violating Mass. Gen. Laws ch. 142A, 17(10) is subject to the six-year statute of repose set forth in Mass. Gen. Laws ch. 260, 2B.In 2016, Plaintiff brought this action alleging that renovations performed in 2000 to 2001 by Defendants caused a fire in her home in 2012. A superior court judge dismissed the complaint as untimely under the six-year statute of repose. The Supreme Judicial Court affirmed, holding (1) Plaintiff’s chapter 93A claim was sufficiently tort-like to bring it within the ambit of the statute of repose; and (2) because this action was commenced more than six years after the work was completed, it was barred by chapter 260, section 2B, and therefore properly dismissed. View "Bridgwood v. A.J. Wood Construction, Inc." on Justia Law

by
The Division of Capital Asset Management and Maintenance (DCAM), the owner of a construction project, entered into a contract with a designer to prepare the project’s designs. DCAM contracted with Gilbane Building Company to be the construction manager at risk (CMAR). Gilbane subcontracted with Coghlin Electrical Contractors, Inc. to perform electrical work. Coghlin later filed a complaint against Gilbane alleging that Gilbane breached the subcontract by causing Coghlin to incur additional costs resulting from design errors. Gilbane filed a third-party complaint against DCAM, asserting that DCAM breached its contract with Gilbane by refusing to pay Gilbane the amounts claimed by Coghlin. The trial court allowed DCAM’s motion to dismiss the third-party complaint. The Supreme Judicial Court vacated the superior court’s judgment, holding (1) a public owner of a construction management at risk project gives an implied warranty regarding the designer’s plans and specifications, but the scope of liability arising from that implied warranty is limited; (2) the construction management at risk contract in this case did not disclaim the implied warranty; and (3) the contract's indemnification provision did not prohibit Gilbane from filing a third-party complaint against DCAM seeking reimbursement of additional costs under the implied warranty for damages claimed by Coghlin caused by an insufficient or defective design. Remanded View "Coghlin Elec. Contractors, Inc. v. Gilbane Bldg. Co." on Justia Law

by
Ayer Properties, LLC (Ayer) purchased and converted a building into condominiums. Trustees of the Market Gallery Condominium Trust (trustees) filed an action against Ayer seeking damages stemming from Ayer’s negligent construction of elements of the building. A superior court judge found Ayer was negligent in its construction of window frames, masonry, and roof. However, the judge concluded that the economic loss rule precluded the trustees from recovering for damage resulting from the defective masonry work because it did not cause damage to any individual units. The Supreme Judicial Court (1) affirmed the judge’s decision as to the window frames and roof and remanded for entry of an order awarding additional damages for the negligently constructed masonry; but (2) reversed the judge’s decision to reduce the repair and replacement damages by twenty percent and remanded for entry of judgment in the full amount of damages established at trial. View "Wyman v. Ayer Props., LLC" on Justia Law

Posted in: Construction Law
by
Plaintiff, a subcontractor, filed an action to enforce a mechanic's lien on certain land. More than a year later, Defendants, acting as principal debtor and the surety, executed and recorded a surety bond to dissolve the lien pursuant to Mass. Gen. Laws. ch. 254, 14. The bond named Plaintiff as an obligee. Plaintiff subsequently amended its complaint to include Defendants as defendants in the underlying complaint and to add a claim to enforce the bond against them. At issue was whether Plaintiff's amendment of its original complaint constituted timely commencement of its action to enforce a bond pursuant to section 14. The lower court found that although Plaintiff had not filed the amended complaint within ninety days of receipt of notice of the bond, service of its motion to amend on Defendants within that ninety-day period satisfied the section 14 requirement that a claimant have "commenced" a civil action within that period in order to enforce the bond. The Supreme Court affirmed, holding that the commencement requirement in section 14 was satisfied on the facts of this case because the amendment to the complaint related back to the date on which Plaintiff filed its original action against Corporation. View "Nes Rentals v. Me. Drilling & Blasting, Inc." on Justia Law

by
After falling down a staircase at a bar and restaurant in Boston, a college student died. Plaintiffs, the student's parents, filed this action against the restaurant and trustees of a trust that owned the land and buildings within which the restaurant operated. The complaint alleged claims against the restaurant and trustees for wrongful death and for violation of Mass. Gen. Laws ch. 93A. Plaintiffs based their chapter 93A claim on Defendants' alleged building code violations, which Plaintiffs claimed constituted unfair or deceptive conduct. A jury returned a verdict for Defendants on Plaintiffs' wrongful death claims, and the trial judge found in favor of Plaintiffs on the chapter 93A claim, finding that the student fell and suffered a fatal injury because the stairs were in an unsafe, defective condition having been rebuilt without necessary building permits. The Supreme Court vacated the judgment, holding that Plaintiffs were entitled to recover on their chapter 93A claim but that the judge erred in her calculation and award of damages. Remanded. View "Klairmont v. Gainsboro Rest., Inc." on Justia Law

by
Construction Company contracted with Subcontractor for construction of elements of an HVAC system. As partial collateral for a revolving line of credit, Subcontractor assigned to Bank its right to receive payment under the contract with Construction Company. Construction Company instead made twelve payments to Subcontractor. Subcontractor subsequently ceased business operations, leaving an outstanding debt to Bank on its line of credit. Bank filed an action against Construction Company for breach of contract and violation of the UCC. A jury found (1) Construction Company liable on both counts for ten of the twelve checks that it had delivered to Subcontractor, and (2) Bank was estopped from recovering with respect to the final two checks. The judge entered judgment on the statutory claim in the amount of $3,015,000, the full face value of the ten checks. The Supreme Court affirmed in part and reversed in part, holding that the trial judge (1) properly entered judgment on Bank's statutory claim in the amount of the wrongfully midirected payments; but (2) erred in denying the bank's motion for partial judgment notwithstanding the verdict with respect to the final two checks, as there was insufficient evidence to support Construction Company's defense of estoppel. View "Reading Coop. Bank v. Constr. Co." on Justia Law